|

May 5, 2003 The
first day, before any demolition began. |

May 6, 2003 The
trees north of the building had to be removed. |

|
|

May 7, 2003
On a very cloudy day, the pavement in the parking lot is removed. |

|

|
|

And
demolition begins inside. This is the former adult area. |

|

This
is the former children's area. |
|

Looking
from the children's area toward the adult area. There used to be a
staff lounge and offices here. |

That's
a Bobcat... in the foyer. |
|
|

May
22, 2003 As demolition continues, the foyer is removed,
exposing the front of the Carnegie part of the building. |
 |
 |
|

July
2003 The basement excavation has begun. The metal sheeting
will keep the foundation of the Carnegie Building from shifting. |

|

Footings
have been poured for the basement walls. |
|

Rainwater
in the excavation has been a constant problem. |

More
water. |
|
|

Aug.
2003 Forms used to pour basement wall.
|

|

|
|
|

|
|
|

Aug.
2003 Our first basement walls!
|

|

|
|

Aug.
2003 Framing begins for the walls of the new meeting room.
|
 |
|
|
Sept.
2003 Forms in place as the north wall of the basement is poured.
|

The
front of the Carnegie building.
|

Walls
are already poured on the east end. |
|

Oct.
30, 2003 The first roof truss is set in place!
|

New
brick completed on the south side of the building and continuing around
the 1988 addition. |

The
north side of the new addition. The 2 large windows will be on
either side of the fireplace. |
Nov.
4, 2003 Roof trusses continue to go up.
|

This
will be the reading area with the fireplace.
|
|
|

Nov.
13, 2003 The masonry is nearly completed on the north side
of the addition. The white squares will be light fixtures.
|

The
west side of the building. |
|
|

Dec.
3, 2003 The inside of the addition.
|

|
The
elevator shaft.
|
|

The
west side of the addition.
|

View
from the east. |
|
|

Dec.
17, 2003 Interior views of the addition, including the fireplace.
|
|
|
|

Jan.
28, 2004 The west side of the addition which will be the new main
entrance on Elizabeth Street.
|

The
east side of the building on South Wayne Street.
|
|
|

Feb.
18, 2004 The reading room and fireplace. The green styrofoam
will be replaced with blue art glass.
|

The
adult services area.
|

The
circulation desk area and offices.
|
|

The
meeting room and the north face of the Carnegie building.
|
|
|
|

March
18, 2004 The area behind and around the circulation desk.
|

The
railings around the original Carnegie building.
|
The
fireplace room.
|
|

This
is the ceiling of the fireplace room and the freshly stained ceiling slats.
|

The
new children's area just as they are preparing to paint.
|
|
|

March
31, 2004 The finished fireplace room ceiling. The window
trim is also installed.
|

The
columns in the children's area have new shelves built around them for
display.
|

More
painting and wood trim completed.
|
|

Main
entrance and foyer.
|

Meeting
room kitchen and staff lounge.
|
The
staff lockers are installed.
|
|

The
repainted entrance to the Carnegie building.
|
The
still-in-progress technical processing and server rooms.
|

The
main circulation area and staff workroom.
|
|

April
6, 2004 The Children's Services desk.
|

Carpet!
|
|
|

April
28, 2004 The adult services and circulation areas. Carpet
installation and painting are nearly done.
|

The
circulation area viewed from the 2nd floor elevator landing.
|

The
reference room in the Carnegie building is awaiting paint and carpet.
|
|

May
12, 2004 The parking lot is graded and awaits asphalt.
|

Shelving
is being installed in the Children's Dept.
|

Chairs
have been delivered and the fireplace insert is installed.
|
|

Shelving
in the Adult Service Dept.
|
Plumbing
fixtures are installed.
|
|
|

May
26, 2004 Light fixtures in Reference Dept. in the original
Carnegie building.
|

Shelving
and furniture in the Children's Dept.
|

Oak
shelving being installed in the fireplace reading room.
|
|

The
new reference desk.
|

Circulation
area.
|
|
|

The
library staff spent most of the month of June 2004 moving back into the
expanded library. First,
we started packing books at the temporary location.
|

Then
we tear down and move the shelves to unpack books at the new library.
|
|
|

Since
the elevator was unfinished, we moved books to the upper level with a
conveyor on the stairs.
|

We
worked in a sea of boxes while shelving was rebuilt.
|

|
|

One
day, Margaret grilled hot dogs in the parking lot. Notice the creative
use of the book cart.
|
|
|

Finally!
Opening day, July 2, 2004. The Children's Dept. bravely scheduled a
storytime for the very first day we were open.
|
|
|